2021

December 2021: Interviewed for the Design Services position were held on the 21st of this month.

October 2021: Board approved the Owners' Representative Contract with RFC Contracting. Board authorized Director to solicit Statements of Qualifications for Design Services.

September 2021: Board authorized the hiring of RFC Contracting as the Owners' Representative.

July 2021: Interviews for the Owners' Representative position were held on the 19th and 20th of this month.

May 2021: Board authorized Director to revise the deadline to receive Statements of Qualifications to allow for additional candidates.

April 2021: Board authorized Director to solicit Statements of Qualifications for Owners' Representative.

 

Stakeholders and patrons are encouraged to stay up-to-date during the Library renovation project by visiting the Library Renovation section of the website, signing up for our eNewsletter, and following us on social media.